PALM BAY, Fla. (The Palm Bayer) Between the morning of November 4, 2026 and 3 PM on November 9, 2026, the reject tank at Palm Bay’s North Regional Water Reclamation Facility overflowed an estimated 3,196,440 gallons of reclaimed water. Reclaimed water is treated wastewater that is kept for reuse. The reject tank holds the treated water that cannot be reused. The 3,196,440 gallons is the city’s final estimate, in its filing to the Florida Department of Environmental Protection, incident 2026-11299, for 1080 Clearmont St NE. The day before the overflow began, the city and the department entered a consent order, a binding legal agreement between the city and the state, OGC #25-1559, dated November 3, 2026 in the department’s records. In that order, the city admitted that corrosion in the plant’s reject tank had caused a release on May 5, 2026.
The spill
According to the city’s filing, the plant’s reclaim tank filled, and the reject tank was filled as last-resort storage and overflowed. The city’s interim estimate on November 6 was about 2.98 million gallons. Its final figure, 3,196,440 gallons, appears in the city’s November 10 update. That update records that the spill ceased at 3 PM on November 9.
The same storm window produced other releases in the city’s filings. A deep well trough at 1105 Clearmont St NE overflowed about 105,000 gallons of reclaimed water (incident 2026-11300). Five lift stations, the pump stations that move wastewater through the system, also spilled raw wastewater in the same window, a combined total of roughly 613,800 to 834,800 gallons across the city’s reported ranges:
- LS70, 270,000 to 432,000 gallons
- LS9, 90,000 to 144,000 gallons
- LS5, 172,800 gallons
- LS27, 72,000 gallons
- LS48, 9,000 to 14,000 gallons
Every city notice attributes the event to 24 inches of rain in under 24 hours on November 2 and states the city’s position: “Absolutely nothing could have prepared us for this catastrophic flooding event.”
More rain forecast
Palm Bay is under a Flood Watch issued by the National Weather Service in Melbourne, in effect through 7 PM on Friday, November 20, 2026. The watch carries additional rain in the forecast for ground that is already saturated. The November overflow at the plant followed the heavy rain of November 2. The Palm Bayer’s coverage of the forecast, More Rain on Soaked Ground, carries the week’s full forecast.
The record before November
The November overflow is the latest in a series of releases at the plant, and the state filings and council packets document each earlier release separately.
The May report
In May 2026, the city filed its own report with the department on the condition of the reject tank (PNP 20264057, reported May 7, 2026). The report states: “Several rust holes have developed on the reject tank, indicating ongoing corrosion and deterioration… We have welded the patches over the rust holes. A plan should be developed for the complete remediation or replacement of the tank.”
The consent order records the related release. On May 5, 2026, 7,600 gallons of under-disinfected wastewater were released “from excessive corrosion in the reject tank at 1105 Clearmont St. NE.”
The consent order
The consent order covers facility FLA103357, the Palm Bay North Regional Water Reclamation Facility. The plant’s permit allows 5.2 million gallons per day. In the order, the city admitted:
- June 8, 2025: the break of a 20-inch force main, a pressurized pipe that carries sewage, at 1050 Clearmont St, which released about 2,410,000 gallons of raw sewage.
- 2024 and 2025: required groundwater monitoring parameters were not analyzed.
- February to April 2026: three contractor-caused spills, of 16,500, 13,500, and 15,000 gallons.
- May 5, 2026: the reject tank release.
The order also records the department’s June 30, 2026 inspection. The inspection rated the facility Out of Compliance overall and stated: “Corrosion was noted throughout the WRF plant.” A Corrosion Control Plan was emailed to the city on July 22, 2026.
The order requires a detailed corrosion inspection, with findings due within 30 days of the effective date, about December 3, 2026. Corrective actions must be complete within 548 days, with quarterly progress reports. The penalty is $23,980: a $23,480 civil penalty plus $500 in costs, payable within 90 days. The city may offset the $23,480 with a Pollution Prevention project. Stipulated penalties, the penalty amounts the order sets in advance, run $1,000 per day for late compliance, plus an amount for each discharge based on its size, up to $15,000 for a discharge over 100,000 gallons. On the face of that schedule, $15,000 is the amount set for a discharge of the November overflow’s size. Whether the department will demand stipulated penalties for the November overflow is not established in the record, and no demand is recorded.
What council was told
Council received a full briefing on the June 2025 force main failure. The July 17, 2025 packet carried Utilities Director Bowden’s slide deck, “1050 Clearmont Spill, Council Update.” The deck records that the pipe failed Sunday, June 8, 2025 at about 9 PM, that staff were on site at 10 PM, and that containment was in place at 10:30 PM. The emergency operations center opened June 9. Of the 2.41 million gallons discharged, 1.25 million were recovered and 1.16 million were released to Turkey Creek. The pipe was installed in 1988. On September 4, 2025, council approved emergency procurement 5-0 and appropriated $1,138,725 (Cathcart, $1,124,192; Goodson Paving, $14,533). The September 4 staff memo states: “FDEP has been fully briefed on the spill and is expected to issue a fine in the range of $15,000-$40,000. The Department anticipates that FDEP may reissue the current consent order, separating plant-related and collection system-related requirements. Staff have requested extended time to develop a community-supported water quality improvement project to offset any fines.”
In spring 2026, City Manager Matthew Morton told council on the record: “We violated our permit. Last year. It’s not a secret. We are risking violating our permit today, just based on flows.” Plant flows went over the plant’s permit of 5.2 million gallons per day several times, reaching over 5.4 million gallons per day in October 2025.
What never reached council
Across the packets of all 52 council meetings from June 2025 through November 17, 2026, the executed consent order appeared on no agenda. The words “reject tank” appear in no packet. The May 2026 corrosion release appears in no packet, including the packet for the May 7, 2026 meeting, two days after the release. No plan to repair or replace the tank, no corrosion program, and no tank line item was presented in any packet. The adopted FY27-31 capital plan funds North Regional force main construction ($1,499,800 in FY27) and plant rehabilitation ($2.63 million funded in FY27, with $12.5 million unfunded in FY28-30). It contains no reject tank or corrosion project.
Two meetings
On October 15, 2026, council approved $230,250 to Meeks Plumbing for digester repair at the plant, on the consent agenda. The staff memo notes that the department “also identified corrosion and deterioration associated with the digesters” during its inspection. The memo does not mention the consent order, the Out of Compliance rating, or the reject tank.
On November 5, 2026, while the overflow was in progress, council approved a $398,800 Kimley-Horn task order. The order designs a new force main connecting to “the existing 20-inch PVC force main in the Clearmont Street right-of-way,” the pipe that failed in June 2025. The packet mentions neither the failure nor the overflow.
The longer record
The plant’s inspection and repair record extends back years. In 2020, inspectors documented severe erosion at the headworks, the plant’s intake, with exposed rebar, seepage, and a failed clarifier, a settling tank. About a year of excess biosolids, treated sewage solids, went to earthen ponds, with a failed cake pump. A 2022 storage tank inspection found corrosion and pitting on discharge piping. In January 2024, the city rehabilitated Digester 1 for $227,000. On July 2, 2026, council approved $501,120 to Cathcart for pond cleaning and valve replacement, on the consent agenda. At the September 2025 budget hearing, Bowden stated that the North plant needs $10 to $15 million to meet future nutrient limits.